Manage Projects with Gantt Charts

TopLeft shows your project tasks in Gantt charts so you can understand the timing of projects and tasks.

The Gantt chart of the Downtown Office Move project, with tasks listed under their phases and blue bars by date

Manage an Individual Project in Gantt

You can use TopLeft Gantt charts to manage the tasks within a single project. Tasks are listed within their phase.

An arrow from task 1774 to task 1768 showing that 1774 must finish before 1768 starts

In regards to dependencies, the task predecessors, when set in the PSA, are shown in the Gantt chart. In the above image, task 1774 is the predecessor of task 1768. 

You can change the start or end date of a task from the chart:

  • To change the task start date, drag the left side of the bar
  • To change the task end date, drag the right side of the bar
  • To change the start and end date together, drag the body of the bar

How to Access the Gantt Chart

There are two ways to open the Gantt chart for an individual project.

  1. From a project overview board: on a Kanban board that shows projects, each project card has a link to the project's Gantt chart:
    A project card with its Gantt chart icon highlighted
  2. From a project or phase swimlane board: on a Kanban board that shows tickets or tasks grouped by projects or project phases, the swimlane header includes a link to the project's Gantt chart:
    A project swimlane header with its Gantt chart icon highlighted next to the project name

Manage a Project Portfolio in Gantt

You can also use TopLeft Gantt charts to manage your project portfolio.

The project portfolio Gantt chart, one bar per project, with overdue projects in red

This view shows only your top-level projects and not their tasks.

You can change the start or end date of a project from the chart by dragging either the left side, left side, or the whole bar.

How to Access the Project Timeline

To open the project timeline, browse to a project board (where cards represent projects), and click the timeline icon in the main menu:

The timeline icon in the main menu

The timeline shows the same projects as are shown on the project Kanban board.

Manage Multiple Projects in Gantt

You can also manage the tasks within multiple projects in Gantt.

The multiple-project Gantt chart, with each project's tasks listed under it and dependency arrows between bars

This view shows the timing of multiple projects and their tasks. Phases are not shown in this view.

You can change the start or end date of a project or task from the chart by dragging either the left side, left side, or the whole bar.

How to Access the Multiple Gantt Chart

To open this view, browse to a ticket/task board where the swimlane is set to Project or Phase. Then click the timeline icon in the main menu:

The timeline icon in the main menu

The chart shows the same projects and tasks as are shown on the Kanban board.

Monitoring Progress and Budget Overage

TopLeft Gantt charts can help project managers understand their project progress and react quickly to problems.

The colouring of the bar indicates the progress:

Gantt bars where the dark part shows hours logged against budget and red bars show work over budgetThe dark part of the bar indicates how many hours have been logged relative to the work's budget. For example, this would indicate about 80% of the budget had been used:
A Gantt bar with most of its length dark, showing most of the budgeted hours logged

When work exceeds the budget, it is shown in red:

A Gantt bar shown entirely in red because the work is over budget

This applies to both tickets, tasks, and projects. If a ticket, task, or project has no budget, no coloring is applied.

Updated September 23, 2026

Comments

    The first time, we email you a link to confirm. After that, this browser remembers you.

    Like

    We email you a link once. After you click it, this browser remembers you on every docs page.

    Feedback on this page

    Fix or keep
    What kind

    Tip: select words on the page before you open this, and they come with your note.

    Optional, up to 5. Paste into the box above, or drop them here.

      They go into the GitLab issue. Crop out anything private.

      See every note and what happened to it